October 8, 2026
Swimmers at 595 North Franklin Street were getting more than chlorine. In a June 2025 letter to Christiansburg Town Council, Town Manager Randy Wingfield said rust was dropping from the ceiling onto customers and employees and running down the windows and walls. He said ceiling panels were being replaced every few weeks because mold had turned up in the offices. "Ceiling insulation in the form of white, soft chunks, is falling onto staff and patrons in the water," he wrote.
The pools were never the problem. Since then the Town has budgeted more than $11 million for the building's air, and you won't see most of that work from the water. The best way to judge it is the October calendar. Virginia Tech hosted a swim meet there today, and later this month the facility runs a Halloween workout in the deep end of the competition pool, which closed for HVAC work in late May.
An indoor pool is a humidity machine, and the Aquatic Center had no dehumidification system to handle it, according to Wingfield's letter. His letter drew on a Setty HVAC evaluation of the building, released July 31, 2023, which explained why the air felt bad. Organic material from swimmers reacts with chlorine coming off the water and forms chloramines, which are heavier than air. If treated air doesn't displace or dilute them, they cause air quality problems in the breathing zone, where swimmers can feel them.
Setty didn't blame the equipment alone. The report said the poor air quality readings came from "a combination of water chemistry issues and less than optimal mechanical ductwork distribution layout." Its conclusion was still replacement. The report cited the units' age, their poor financial efficiency and their inability to meet the air standards in the Model Aquatic Health Code and ASHRAE guidance.
That explains where the money went. The Town replaced the air handling and the way air moves across each pool deck, not the pools or the lanes.
Wingfield's letter showed that the damage went past what patrons could see. In his account, the humidity had spread through the building and into the budget:
The letter also said patrons and athletes had reported going to the emergency room with coughing, asthma, headaches and other illnesses. These were reports passed along to officials, not medical findings. Still, they helped explain why council members treated the project as urgent. Council member Johanna Hicks called the air quality "a health hazard right now" and moved the contract to a work session to get more warranty information. Council member Tanya Hockett said action was an "urgent need" and noted that the Town had already saved money for the project.
The swim meets are the item to watch. Lost meets were the cost that showed up in local hotels and restaurants as well as in the pool's own books. A full collegiate meet back on deck is the clearest public sign the building can compete again.
The construction contract before council in June 2025 was $10.587 million. In April 2026, Cardinal News reported the full HVAC project at more than $11 million across two budgets: $9.5 million in the 2025–26 budget and another $1.6 million proposed for 2026–27. That spending came in a budget that proposed no tax increases.
The Town worked through the building in phases so parts of it could stay open:
The facility calendar listed the competition pool as closed for HVAC work on May 27, 2026. The late-July date was a forecast. The board's August 5 agenda still listed "Competition pool reopening date" as a discussion item. The public record doesn't give an exact reopening date. It does show where things stand now. On October 3, Virginia Tech hosted a women's tri-meet at the Christiansburg Aquatic Center, where the Hokies beat Liberty 240-113 and Penn State 312-41.
This month's calendar uses the whole building, including the deep competition pool that was the last area to come back. For residents, these are the dates to know, all at 595 North Franklin Street:
These events are a simple way to judge the air for yourself. When the competition pool was last fully open, the Town Manager was describing rust on the windows and insulation in the water. A crowded Friday family night and a deep-water class are the conditions the new system was built to handle.
The HVAC work is only the first project on the site. In April 2024, Town Council approved a power purchase agreement with Sun Tribe Solar for rooftop solar at both the Recreation Center and the Aquatic Center. The News Messenger reported combined carbon-emissions avoidance of 11,480 tons for the two buildings. By the June 2026 board meeting, the Aquatic Center installation was substantially complete, and MEI was waiting on a telemetry device.
The same minutes said construction on the H2Okie Dryland Fitness Building will start once the HVAC work is finished. When the project was announced in August 2025, the Radford News Journal described a 1,500-square-foot facility where H2Okie swimmers would train out of the water, with no competitions planned there. It would go on a lot behind the Aquatic Center at Mill and Depot streets under a 30-year agreement with the Town. The estimated cost then was about $800,000, split three ways among the club's reserves, local financing and a capital campaign. Kessler Construction was expected to build it over about six months. Those cost and timing figures date from 2025. The June 2026 minutes give the order of work but no updated cost or start date.
As of the June meeting, the grand opening for the renovated center was unscheduled, and the minutes listed the date as "to be determined." The Oct. 7 advisory board meeting is the next public setting where the date could come up.
A building's mechanical systems rarely make a listing sheet, but buyers end up living with them. If you're weighing a Christiansburg home, are curious what an aging HVAC system might be costing you, or just want a local read on what the Town is investing in near North Franklin Street, Wendy Swanson and the Swanson Team are glad to talk it through, with no pressure and plenty of local context. Contact Us whenever you're ready.